Skip to content
Demo
Company 15 min read

EV charging infrastructure in Switzerland explained: components, modes and Swiss standards

EV charging infrastructure in Switzerland: components, AC/DC, the 3.7 kW rule, NIV, NIN 2025, SIA 2060 levels, subsidies and right-sized costs.

Aubin Aycaguer, Chief of Staff, Voltaback9 Nov 2026

Diagram of EV charging infrastructure from the distribution board to the charging station and the electric car

EV charging infrastructure is the whole installation that brings electricity from the grid to the car: grid connection, distribution board, protection devices, dedicated circuit, charge point and usually load management and metering. The charging station or wallbox is only the visible part.

If you have installed chargers elsewhere in Europe, much of this will look familiar, but Switzerland has its own sockets, its own grid-operator rules and its own standards. This guide maps each component, AC and DC charging, the four charging modes, the power limits set by network operators, who may install and how to check them (NIV, NIN 2025, safety certificate), the SIA 2060 readiness levels, the rules that apply, subsidies and what a right-sized installation costs.

Voltaback works with more than 200 companies on fleet charging. Companies such as Sodexo, Siemens, BNP Paribas and Sanofi use Voltaback. We do not install chargers, but we help choose the right setup for each employee and then reimburse home charging at real cost.

Updated 4 November 2026.

Charging infrastructure or charging station: what is the difference?

Charging infrastructure (Ladeinfrastruktur / infrastructure de recharge / infrastruttura di ricarica) is the complete system. The charging station or wallbox is the device on the wall or on a post. A station without a properly sized circuit, the right protection or notification to the network operator cannot be commissioned.

A short glossary for newcomers:

  • Charge point: a place where exactly one vehicle can charge at a time. A charging post may have two.
  • Wallbox: a wall-mounted AC charging station, typical for a garage or underground car park (Einstellhalle / parking souterrain).
  • Charging post: a free-standing station, usually on company or customer car parks.
  • Basic installation (Grundinstallation / installation de base): everything upstream of the station, meaning connection, board, main feeder and supply line.

Why this matters for a fleet manager:

  • Cost: in an existing underground garage, cabling and the distribution board often cost more than the wallbox.
  • Procedures: it is the electrical installation that is notified to the network operator and inspected, not the device.
  • Scalability: well-prepared infrastructure (SIA 2060 levels) lets you add chargers later without major works.

What are the components of EV charging infrastructure?

From the street to the car, electricity passes through seven stages. Each has its own job and its own cost.

1. Grid connection

Everything starts at the building's connection to the distribution network operator (Verteilnetzbetreiber, VNB / gestionnaire de réseau, GRD): ewz or EKZ around Zurich, SIG in Geneva, WWZ in Zug, IWB in Basel, Romande Energie or municipal utilities in Vaud. The capacity of that connection caps what you can install without an upgrade.

If it is not enough, there are two routes: have the operator reinforce the connection (expensive, with a waiting time) or cap the charging power with load management (usually the better choice).

2. Distribution board and dedicated circuit

The charger is fed by a dedicated circuit from the main board or a sub-board. Cable size depends on power and length. In shared garages a main feeder (often a flat cable) serves several spaces, and each charger is connected to it.

3. Protection devices

The Swiss low-voltage installation standard (NIN, SN 411000, the local equivalent of IEC 60364), in its 2025 edition in force since 1 January 2025, has a dedicated part on supplying electric vehicles (part 7.22). Each charge point needs its own overcurrent protection and a residual current device that also detects DC faults: either a Type B RCD, or 6 mA DC detection built into the charger combined with a suitable RCD. The installer makes the final choice.

Source: Electrosuisse e-mobility brochure.

4. Charge point

This is the station and its connector. The European standard for AC charging is the Type 2 connector (IEC 62196-2), and for DC charging the CCS connector. The cable is either tethered to the station or brought by the driver.

5. Load management

With several chargers, load management shares the available power so the building connection is never overloaded. There are two kinds:

  • static: fixed limits per charge point or group;
  • dynamic: limits recalculated continuously from live measurements at the connection, including output from a solar installation.

Both also balance the load across the three phases. The handbook of the Association of Swiss Electricity Companies (VSE / AES) recommends the following total charging power for residential buildings:

Number of charge points

Fuse

Recommended total charging power

1 to 5

13 A

9 kW

6 to 14

16 A

11 kW

20 to 29

32 A

17 kW

30 to 39

40 A

22 kW

50 to 99

80 A

55 kW

100 and more

160 A

111 kW

Source: Stadtwerk Winterthur e-mobility sheet. Other building types may need different sizing.

6. Backend

Networked chargers connect to a management platform, usually via the open OCPP protocol. The backend handles access badges, user rights, billing and fault alerts. It makes sense in a shared car park and is rarely essential at home.

Insist on OCPP compatibility: it lets you change platform provider later without replacing the stations.

7. Metering

To bill electricity to a third party or separate the car's consumption, you need a meter, ideally MID-certified, in the charger or the board. Some subsidy programmes require it: Basel-Stadt, for example, requires a utility meter for its grants.

AC or DC: what happens inside the car

The battery stores direct current (DC), while the grid delivers alternating current (AC). The conversion has to happen somewhere.

  • AC charging (wallbox, socket): the car's on-board charger converts the current. Its rating caps the charging speed. Many models accept 11 kW, some 22 kW, and some older or entry-level models only 7.4 kW.
  • DC charging (rapid charger): the station converts the current itself and feeds the battery directly. Power depends on the station, the car and the battery's state of charge.

The planning consequence: a 22 kW wallbox brings nothing to a car with an 11 kW on-board charger. It costs more, needs a heavier supply cable and requires the operator's approval. Check the AC charging power of the cars in your fleet before ordering anything.

Bidirectional charging (the car returns power to the home or grid) is still emerging in Switzerland. It needs an approved car and a compatible station. The canton of Ticino already supports such stations with a higher grant (see subsidies below).

The four charging modes and Swiss sockets

The international standard IEC 61851 defines four charging modes. Switzerland adds its own domestic sockets, which differ from those used in neighbouring countries.

Mode

Connection

Typical power

Use in Switzerland

Mode 1

Domestic socket, no safety device in the cable

Low

E-bikes and scooters, not cars

Mode 2

T13, T23 or CEE socket with an in-cable control box

About 2.3 kW on T13; about 3 kW on T23; 3.7 kW on single-phase blue CEE16; up to 11 kW on red three-phase CEE16

Emergency or slow home charging

Mode 3

Fixed charging station or wallbox, Type 2 connector, AC

3.7 to 22 kW

Standard at home and in company car parks

Mode 4

DC rapid charger (CCS)

50 to over 300 kW

Motorways, rapid charging hubs

T13 and T23 domestic sockets are not designed for several hours of continuous load, and network operators advise against using them for regular charging. A CEE industrial socket fitted by an installer, or a wallbox, is the safer option. Our comparison of the best socket for charging an electric car covers the choices.

Which power: from 2.3 to 22 kW

Swiss network operators' technical connection rules (Werkvorschriften, WV-CH) contain a rule that often surprises newcomers: single-phase charging is capped at 3.7 kW (230 V, 16 A), two-phase at 7.4 kW. The single-phase 7.4 kW wallbox common in some other countries is therefore not a standard option here. Above 3.7 kW, you go three-phase.

Power

Supply

Energy in 8 hours

Range at 18 kWh/100 km

2.3 kW

Single-phase, T13 (emergency)

About 18 kWh

About 100 km

3.7 kW

Single-phase 16 A

About 30 kWh

About 160 km

11 kW

Three-phase 16 A

About 88 kWh

Full battery for most models

22 kW

Three-phase 32 A

Full battery

Only useful if the car accepts 22 kW AC

Worked example: a 40 km daily commute in a car using 20 kWh/100 km needs about 8 kWh, a little over two hours at 3.7 kW. Most company cars therefore recharge comfortably overnight at low power, which also spares the grid.

Two further rules apply at most network operators:

  • Above 3.7 kVA, the charger must be controllable by the network operator, usually through a ripple control receiver (Rundsteuerempfänger, RSE). It can temporarily reduce charging power to stabilise the grid.
  • Above 11 kW, the operator has to approve the installation before commissioning; up to 11 kW, notification is enough.

Sources: Stadtwerk Winterthur, CKW, legal requirements for charging stations. Details vary between operators, and your installer will know the rules for your municipality.

Worked example: 20 spaces on a company car park in Geneva

A company in the canton of Geneva wants to equip 20 parking spaces. Without load management, 20 chargers at 11 kW would need 220 kW of connection capacity, which a standard commercial connection rarely provides.

The real need looks different:

  1. Each car drives 50 km a day on average at 20 kWh/100 km, so it needs about 10 kWh a day.
  2. Twenty cars need about 200 kWh per working day.
  3. Spread over a 9-hour parking time, that is an average of about 22 kW.
  4. With dynamic load management and a reserve of about 40 to 60 kW, every car is charged by the evening.

Load management here replaces an expensive reinforcement of the building connection. The installer sets the exact reserve after measuring the existing load.

Who may install EV charging infrastructure in Switzerland?

A fixed charger is a low-voltage electrical installation. The Low-Voltage Installation Ordinance (NIV / OIBT, SR 734.27) restricts this work to holders of an installation permit issued by the Federal Inspectorate for Heavy Current Installations (ESTI). In practice you hire a licensed electrician (konzessionierter Elektroinstallateur / installateur-électricien concessionnaire).

The process step by step:

  1. Get consent: tenants ask their landlord, condominium owners need a decision of the owners' meeting. In a detached house you own, this step falls away.
  2. Before work starts: the installer files a technical connection request (technisches Anschlussgesuch, TAG) and an installation notice (Installationsanzeige, IA) with the network operator. All chargers must be notified, including portable units on an existing socket.
  3. Wait for approval: only needed above 11 kW.
  4. During the work: the installation complies with NIN 2025, especially part 7.22.
  5. After the work: the installer issues a safety certificate (Sicherheitsnachweis, SiNa / rapport de sécurité) with measurements and test report, hands it to the owner and the network operator and reports completion.

An employee therefore cannot fit a wallbox themselves, even one bought online. To get and compare installer quotes, see our charging station installation page.

How to check an electrician

Under Art. 20 NIV, ESTI keeps a public register of installation permits. Network operators check it before work starts, and you can do the same before awarding a contract.

Two kinds of permit matter:

  • General installation permit: covers all low-voltage work, including new circuits, boards and charging stations.
  • Limited installation permit: covers only narrowly defined work, such as connecting certain appliances. It is usually not enough for a new supply line to a wallbox.

Five questions to ask about every quote:

  1. Are the connection request, installation notice and safety certificate included in the price?
  2. Which residual current protection is planned: Type B RCD or DC detection in the station?
  3. Is the station ready for the operator's ripple control receiver?
  4. Is the existing connection capacity sufficient, or is load management included?
  5. Is the supply line sized so that further spaces can be connected later?

SIA 2060 readiness levels

The SIA 2060 technical bulletin "Infrastructure for electric vehicles in buildings", from the Swiss Society of Engineers and Architects, describes five readiness levels, from empty conduit to a working charger:

Level

What is built

Typical timing

A (Pipe for power)

Empty conduits, cable trays, space in the board

New build, shell construction

B (Power to building)

A supply line sized for the charging load

New build or renovation of the connection

C1 (Power to garage)

Main feeder in the garage within 3 m of each future charger

Basic installation in an apartment building

C2 (Power to parking)

Supply brought to each future charger position

Basic installation when demand is foreseeable

D (Ready to charge)

Charger installed and ready to use

When a car arrives

The bulletin is not binding in itself. It becomes binding when a canton refers to it. Bern, Lucerne, Neuchâtel, Schaffhausen and Zurich require at least preparation for later retrofitting in new buildings, Bern for instance through Art. 56a of its building ordinance. For the full cantonal picture, see our article on EV charging obligations in Switzerland.

In practice, level C1 for every space is usually the best investment in an existing underground garage: the main feeder is built once, and each later wallbox costs only the connection and the device.

Which standards and rules apply?

Several sets of rules apply side by side. There is no single law on charging stations.

Rule

What it covers

Binding?

Electricity Act (EleG) and NIV (SR 734.27)

Who may install, notification, inspection, safety certificate

Yes

NIN 2025 (SN 411000), part 7.22

Technical execution: circuit, protection, residual current device

Yes

Network operator's rules (WV-CH)

3.7 kW single-phase cap, controllability, approval above 11 kW

Yes, in the operator's area

IEC 61851 and IEC 62196

Charging modes, car-station communication, connector types

Through product standards

SIA 2060 bulletin

Planning and readiness levels in buildings

Only where a canton refers to it

Cantonal and municipal building law, fire safety

New-build duties, rules for underground garages

Depends on canton and municipality

MID (Measuring Instruments Directive)

Accuracy of meters used for billing

When electricity is re-billed

CKW gives a useful summary of the legal basis. For the details of your building, the network operator is the first point of contact.

Detached house, condominium or company site

Detached house

Apartment building (rented or condominium)

Company car park

Typical charge point

CEE socket or 11 kW wallbox

Wallbox on a shared feeder

Several 11 to 22 kW chargers, sometimes a rapid charger

Consent needed

None, apart from notifying the network operator

Tenant: landlord's written consent (Art. 260a CO). Condominium (Stockwerkeigentum / PPE): owners' decision, usually a double majority (Art. 647d Civil Code)

Landlord, if the company rents

Load management

Rarely

Almost always

Almost always

Metering

Not needed to charge

Needed to split costs

Useful for sharing or re-billing

Who pays for electricity

Employee, reimbursed by the employer

Employee via the service charge statement

The company directly

Condominium source: SFOE and SwissEnergy condominium guide.

Change is under way for tenants and condominium owners. On 19 June 2026 the Federal Council opened a consultation on an amendment to the Energy Act, implementing motion 23.3936: owners of residential buildings could be required to build the basic charging installation when tenants or co-owners ask for it. The consultation ran until 12 October 2026, and nothing has been decided yet. Source: Federal Office of Justice, opening of the consultation (in German).

Today's step-by-step process for owners is in our article on charging stations in condominiums.

Subsidies and VAT in 2026

The Confederation pays no subsidies for private charging stations. Support comes from cantons and municipalities, mainly for basic installations in apartment buildings. Programmes change often, so check conditions before ordering.

Canton

2026 programme (at the time of research)

Zurich

CHF 500.– per parking space (up to 15), CHF 300.– from the 16th, for basic installations in residential buildings; runs until the end of 2026, largely committed

Lucerne

CHF 350.– per space (1 to 10 spaces) in apartment buildings

Basel-Stadt

Grants for charging in underground car parks, with a utility meter required

Ticino

Flat CHF 500.– per charging station at home or at work, CHF 4'000.– for a bidirectional station

Sources: Canton of Zurich, charging infrastructure programme, Canton of Basel-Stadt, e-mobility, Canton of Ticino, mobilità elettrica.

Devices and installation carry 8.1 % VAT (MWST / TVA). A VAT-registered company can reclaim it as input tax when the station is on its own site and used for business. When the employer pays for a wallbox at an employee's home, the salary certificate (Lohnausweis / certificat de salaire) also comes into play: if the wallbox becomes the employee's property, practitioners treat it as a taxable benefit.

What does right-sized charging infrastructure cost?

Not every employee needs a connected charger. Our installation recommendation simulator starts from the following Swiss assumptions, which you can change:

Home installation

Simulator assumption

Share of drivers

Heavy-duty socket (CEE or T23) on a suitable circuit

CHF 600.–

50 %

Non-connected wallbox

CHF 1'800.–

30 %

Installation already in place

CHF 0.–

20 %

Right-sized average

About CHF 840.– per vehicle

Connected charger (for comparison)

About CHF 3'000.– per vehicle

Calculation: 0.5 × 600 + 0.3 × 1'800 + 0.2 × 0 = CHF 840.–. For a fleet of 50 cars, the gap with fitting connected chargers everywhere exceeds CHF 100'000.–. Detailed price ranges are in our article on the cost of installing a home charger.

These figures are orders of magnitude. The real price depends on the distance to the board, the state of the existing installation and the network operator's requirements.

The main cost drivers

  • Distance to the board: every metre of cable, core drilling and fire-stopping costs money. In an underground garage this is often the largest item.
  • State of the board: if there is no room for new breakers, the board must be extended or replaced.
  • Power: 22 kW needs heavier cables and an approval; 11 kW is almost always enough.
  • Load management: needed from a few spaces upwards, a one-off cost per building that becomes cheap per space.
  • Backend and subscription: for connected stations, a recurring cost per charge point and year.

Checklist: planning charging infrastructure for a fleet

  1. Map the need: who drives which car, with which AC charging power and how many kilometres a day?
  2. Set the charging locations: home, company site or public, per employee.
  3. Clarify the housing situation: detached house, tenancy or condominium, with the consent required.
  4. Set the power: 3.7 or 11 kW covers almost every company car; 22 kW only in exceptional cases.
  5. Choose the installer: check the permit in the ESTI register, compare at least two quotes.
  6. Check subsidies: before ordering, not afterwards.
  7. Settle measurement and reimbursement: write into the expense regulations (Spesenreglement / règlement de remboursement des frais) how home charging is reimbursed.

Do you need a connected charger to reimburse home charging?

No. The tax authorities ask for reliable evidence of the kWh and their price, not for a specific device. A connected wallbox is just one way of measuring, and the most expensive.

Voltaback is 100 % software. Charging data are read directly from the vehicle (more than 48 car brands connected) and valued at the employee's real contract tariff: high or low tariff, solar power, self-consumption groups. Voltaback relies on the home's MID-certified meter, not on a standalone cable meter. The measurement was audited by Bureau Veritas, with a 1.22 % relative error.

The company never receives drivers' location data, which simplifies compliance with the revised Data Protection Act (nDSG / nLPD), and Voltaback has been ISO 27001 certified since 2 December 2025. The full comparison of options is in our article on connected chargers for fleets.

Frequently asked questions on EV charging infrastructure in Switzerland

Right-size the hardware, reimburse at real cost

Good charging infrastructure is sized to actual use: low power overnight at home, load management in shared car parks, and no connected wallbox where reliable kWh evidence is enough.

Managing a fleet in Switzerland? In 30 minutes we identify the right setup for each employee and the real cost of their home charging: talk to a Voltaback expert.

Recommended articles