EV charging obligations for company car parks in Switzerland: what the law really requires in 2026

No federal duty for company car parks: MuKEn 2025, SIA 2060 levels, rules in BE, NE, SH, VD, ZH, GE and the right to charge (motion 23.3936) explained.

Aubin Aycaguer, Chief of Staff, Voltaback9 Nov 2026

Accessible parking space with an EV charging station in a company car park in Switzerland

No: in 2026 no federal law requires a company to install charging points in its existing car park. The rules come from cantonal energy and building law, sometimes from municipal regulations, and they apply almost only to new buildings, usually as pre-installed cabling rather than working chargers.

If you have managed facilities elsewhere in Europe, this is the main surprise: Switzerland has no single national rule, and EU building directives do not apply.

This guide maps what does apply, with official sources: module 12 of the cantonal model regulations (MuKEn 2025), the SIA 2060 readiness levels, rules already in force in Bern, Neuchâtel, Schaffhausen, Vaud, Zurich and Lucerne, the planned right to charge (motion 23.3936), the position of a tenant company, the technical steps every charger goes through, the tax and data protection questions of charging on site, and a checklist for each site.

Voltaback works with more than 200 companies on fleet charging, and in our experience the most cost-effective lever is usually at employees' homes, not in the office car park. Companies such as Sodexo, Siemens, BNP Paribas and Sanofi use Voltaback.

Updated 4 November 2026.

The essentials in 30 seconds

  • Federal level: no obligation to equip company car parks. Building rules are a cantonal matter.
  • MuKEn 2025 (adopted 29 August 2025): an optional module asks that at least 20 % of non-customer spaces in new non-residential buildings be ready at SIA 2060 level "C1". Each canton decides whether to adopt it.
  • Cantons: Bern, Neuchâtel and Schaffhausen already set quotas for new buildings; Vaud adds rules for employee spaces from 1 July 2027; Zurich leaves it to municipalities.
  • Right to charge: the federal draft, in consultation until 12 October 2026, covers residential buildings only.
  • For your fleet: the rules count parking spaces, not vehicles. Home charging remains the cheapest option.

Is there a federal obligation to install EV charging points?

No. Under the Federal Energy Act (Art. 45 EnG), the cantons set the rules on energy use in buildings. The Confederation sets targets, funds programmes such as SwissEnergy and regulates vehicles, but it prescribes no number of charging points for any company car park, new or existing.

Three layers of rules can apply to your site:

  1. Cantonal energy law (act and ordinance), which adopts the model regulations of the Conference of Cantonal Energy Directors (EnDK) more or less fully.
  2. Cantonal planning and building law, which sets the required number of parking spaces and sometimes their equipment.
  3. Municipal building regulations (Bau- und Zonenordnung / règlement communal), where the canton gives municipalities that power.

A multi-site company therefore has to check site by site: the same car park project triggers different duties in Bern, Zug or Geneva. Costs and steps are covered in our guide to installing charging stations at work.

Swiss rules versus EU rules: what international companies get wrong

Many group facility teams run a European real estate portfolio from one office. Their reflex is to apply the EU Energy Performance of Buildings Directive (EPBD, recast in 2024) to the Swiss sites too. That directive asks EU member states to require, for example, at least one recharging point for every five parking spaces in new non-residential buildings with more than five spaces, plus pre-cabling, and it sets dates for existing car parks. None of this binds a Swiss building.

Question

EU member states (EPBD transposed nationally)

Switzerland

Who sets the rule?

National law transposing one directive

26 cantons, sometimes municipalities

New non-residential building

Minimum number of recharging points and pre-cabled spaces

Depends on the canton: nothing, conduits only, or a share of spaces at a set SIA 2060 level

Existing company car park

Deadlines for larger car parks

Generally nothing, unless a renovation or a cantonal rule triggers it

Unit counted

Recharging points and pre-cabled spaces

SIA 2060 readiness levels A to D

Right to charge for occupants

Exists in several member states

Planned for residential buildings only, not yet in force

Two practical consequences follow. First, a Swiss subsidiary does not need to reach an EU-style ratio to be compliant: it needs to meet the rules of the canton and municipality of each site. Second, the vocabulary differs. Swiss architects, electricians and building authorities speak in SIA 2060 levels, so a brief written in "recharging points" will be translated back into levels anyway. Write your requirements in levels from the start. Your installer and the building authority will then read the same document the same way.

MuKEn 2025: what does the e-mobility module require?

The cantons' model energy regulations (MuKEn in German, MoPEC in the Romandy cantons) were adopted by the EnDK at its plenary meeting on 29 August 2025. They consist of a basic module, which all cantons are asked to adopt, and optional additional modules.

EV charging sits in module 12, which is optional. It sets two principles: in new buildings, a suitable share of parking spaces must be prepared or equipped for charging; and once basic infrastructure exists, a later charging station may not be refused.

New building

Requirement proposed by module 12 (SIA 2060:2020 levels)

Single-family house

Level "A" for all garage spaces

Apartment building

Level "C1" for at least 60 % of spaces

Non-residential building (offices, workshops, warehouses)

At least 20 % of non-customer spaces ready for use at level "C1", the rest at level "A"

Source: MuKEn 2025, module 12, EnDK, EnDK MuKEn 2025 overview.

What this means in practice:

  • MuKEn is a model, not law. Until your canton writes module 12 into its own legislation, current cantonal rules apply.
  • It asks for prepared spaces, not chargers in service. With 100 staff spaces in a new building, it would mean 20 spaces ready for a charger, not 20 chargers.
  • Customer spaces are excluded from the 20 % rule.

SIA 2060 readiness levels A, B, C1, C2 and D

The SIA 2060 technical bulletin "Infrastructure for electric vehicles in buildings" (2020 edition, under revision) is the technical reference that cantons and municipalities point to. It is a technical bulletin (Merkblatt / cahier technique), not a binding standard: it only becomes mandatory when a law or ordinance refers to it.

Level

Common name

What is built

A

Pipe for power

Empty conduits and cable trays, space reserved in the distribution board

B

Power to building

Plus: a supply line sized for the charging load

C1

Power to garage

A main feeder (often a flat cable) run through the garage, within 3 m of each future charger

C2

Power to parking

Supply brought to the position of each future charger

D

Ready to charge

Charger installed and ready to use

Sources: Canton of Basel-Stadt, levels C1 and C2, Canton of Schaffhausen, levels B and D.

For how the components fit together (protection, load management, metering), see our explainer on EV charging infrastructure in Switzerland.

What do the cantons already require?

The picture is uneven. We checked the rules below in official documents as of 2 November 2026. Other cantons have similar provisions, so always check with the cantonal energy office and the municipality before starting a project.

Bern and Schaffhausen: level D for 20 % of spaces

  • Bern (Art. 56a of the building ordinance, BauV): new buildings for "other uses" and public car parks need level D for at least 20 % of spaces (at least one), level A for the rest. Source: EN-LIEM BE form.
  • Schaffhausen: new or extensively converted non-residential buildings and car parks from 10 spaces, 20 % at level D; existing public car parks with more than 60 spaces, 2 % at level D by 2030. Source: Canton of Schaffhausen.

Neuchâtel, Vaud and Geneva

  • Neuchâtel: since 1 July 2024, all required spaces in new buildings at level B at least; in non-residential buildings, at least 20 % at level D (minimum one, maximum thirty). Source: Neuchâtel Council of State decree of 25 March 2024.
  • Vaud: the new cantonal energy act enters into force on 1 January 2027, its Article 42 on charging on 1 July 2027. In new buildings or car parks, half of the employee spaces need cable conduits and half of those a cable connected to the main board; the act also asks for progressive equipment of employee spaces as the fleet evolves. Source: State of Vaud.
  • Geneva: newer residential buildings must already be pre-equipped, so cantonal subsidies target collective residential car parks with a building permit before 2023: up to 50 % of costs, CHF 500.– per space for the first ten, capped at CHF 20'000.– per car park. These grants concern housing, not company car parks. Source: State of Geneva.

Zurich, Lucerne and Basel-Stadt

  • Zurich: no cantonal quota, but since August 2025 municipalities may set minimum charging readiness for parking spaces in their building regulations (§ 244 para. 4 PBG). Source: Canton of Zurich.
  • City of Lucerne: since 1 August 2026, the amended parking ordinance requires company car parks and parking garages to have 20 % of spaces at level C2, and residential car parks with more than five spaces to have all spaces at level C1. It applies to new projects, renovations and the replacement of the main electrical distribution board. No charger has to be installed. Source: electrive.net.
  • Basel-Stadt relies on subsidies: 60 % of eligible costs, up to CHF 1'300.– per private charging point, programme running until the end of 2030. Source: Canton of Basel-Stadt.

Worked example: a new head office with 80 staff spaces

Location

What 80 staff spaces require

Bern, Schaffhausen, Neuchâtel

16 spaces at level D (charger installed)

City of Lucerne

16 spaces at level C2

Vaud (from 1.7.2027)

40 spaces with conduits, 20 of them with a cable to the main board

Canton adopting MuKEn 2025 unchanged

16 spaces at C1 ready for use, 64 at level A

20 % of 80 is 16. Even in the strictest case, the duty is far from one charger per vehicle. Grants by canton are listed in our article on funding for workplace charging stations.

When an existing building gets caught

Most cantonal rules target new buildings, but three triggers bring existing company sites into scope:

  • Extensive conversion: Schaffhausen applies its quota to new and extensively converted non-residential buildings.
  • Replacement of the main distribution board: in the City of Lucerne, this technical renewal alone triggers the C1 or C2 duty. It is a routine project in older office buildings, so plan the charging readiness at the same time rather than reopening the board two years later.
  • Deadlines for existing public car parks: Schaffhausen requires 2 % of spaces at level D by 2030 in public car parks of more than 60 spaces.

MuKEn 2025 module 12, for its part, sets no requirement for renovations. A canton that adopts it unchanged will therefore leave existing company car parks alone unless its own law adds something.

What each readiness level costs

The obligation is expressed in levels, but the budget is what decision makers want. Orders of magnitude, to be replaced by your installer's quote:

Work

Order of magnitude

Preparing one space in an existing garage (conduit, cable route)

CHF 500.– to 1'500.– per space

Basic infrastructure to level C1 or C2 in a shared car park

Varies widely with the length of the runs and the state of the main board

One installed AC charge point (level D), including fitting

Around CHF 3'500.– per point in a company car park

Source for preparation costs: SFOE / SwissEnergy guide to charging in condominiums (German). The installed point is a typical market figure; power, load management and civil works move it up or down. The cheapest moment is always the shell construction phase: pulling a feeder through a finished underground car park costs several times more.

The right to charge: where does motion 23.3936 stand?

With motion 23.3936 (Grossen), Parliament instructed the Federal Council to secure access to a charging station for tenants and condominium owners (Stockwerkeigentum / PPE) in residential buildings. The Council of States approved it on 11 June 2025 by 24 votes to 18, against the Federal Council's recommendation. An earlier attempt (21.3371) failed in 2023. Source: Swiss Parliament, 11 June 2025.

On 19 June 2026 the Federal Council opened a consultation on an amendment to the Energy Act. The draft provides that:

  • owners of residential buildings may have to build a basic installation when a tenant or condominium owner asks for it;
  • the basic installation covers pre-wiring to the space, a system to allocate consumption and load management;
  • the right applies to people with exclusive use of a space linked to their home, including subtenants, and the work must be reasonable for the owner;
  • for rentals, costs can in principle be passed on through the parking space rent; civil courts settle disputes.

The consultation closed on 12 October 2026. As of this update, the Federal Council has not yet published the results or a dispatch to Parliament, so the text may still change. Source: Federal Office of Justice, consultation notice.

For employees in a condominium today (owners' decision, double majority under Art. 647d of the Civil Code), see our guide to charging stations in condominiums.

Tenant company: who decides on charging stations?

If your company rents its premises, any charging station is an alteration of the rented property. Art. 260a of the Code of Obligations requires the landlord's written consent, and unless agreed otherwise the landlord may ask for the premises to be restored at the end of the lease.

The planned right to charge does not cover commercial leases, only housing, so negotiation remains your lever. Source: Code of Obligations, Art. 260a.

Checklist before the first quote:

  • Who pays for the basic installation and the chargers?
  • Who owns them at the end of the lease, and must they be removed?
  • Which meter records the charging electricity, and who pays for it?
  • Who operates and maintains the system (backend, faults, billing)?

Put the answers in a lease addendum.

From building permit to first charge: the duties that always apply

Whether or not your canton imposes a quota, every charging installation on a Swiss company site follows the same technical and administrative path. These rules apply to the one charger you install voluntarily just as much as to the twenty a canton requires.

1. Building permit and energy proof

For a new building or a major conversion, the charging readiness is shown in the building application, usually in the cantonal energy proof forms (in Bern, for example, the EN-LIEM form cited above). The building authority checks the share of spaces and the SIA 2060 level. A charger added later in an existing car park usually needs no building permit, but a new transformer, a large distribution cabinet or work on a listed building can.

2. Licensed installer and grid operator

Under the Low-Voltage Installation Ordinance (NIV / OIBT, SR 734.27), only a licensed electrical installer may do the work. Before starting, the installer files an installation notice (Installationsanzeige / avis d'installation) with the local grid operator and, depending on power, a technical connection request (technisches Anschlussgesuch / demande de raccordement). Work starts once the operator agrees. Source: CKW, legal requirements for charging stations (German).

3. Load management

Several charge points, or a total above about 22 kVA, usually require load management so that the car park never exceeds the building's connection capacity. Grid operators' technical rules also limit single-phase charging to about 3.7 kVA, which is why Swiss wallboxes charge faster on three phases (11 kW) rather than on one phase at 7.4 kW as in some neighbouring countries.

4. Safety certificate

After the work, the installer issues a safety certificate (Sicherheitsnachweis / rapport de sécurité) with measurement and test reports. Depending on the building's inspection period, an independent check may be required. Keep it with the building file: insurers and buyers ask for it.

With several sites, these four steps run in parallel with different grid operators, each with its own technical rules. Switzerland has around 600 of them, from ewz and EKZ to small municipal utilities.

Charging employees' private cars on site: billing and tax

Once chargers exist, staff with their own electric cars will want to use them. Three questions need an answer before you open the car park.

  • Is free charging a taxable benefit? For company cars, workplace electricity is covered by the 0.9 % monthly private-use charge. For an employee's own car, the salary certificate guidance lists free workplace parking among the benefits that need not be declared (margin note 72), but not charging. In principle, treat free charging as a benefit and clarify it with your seat canton before advertising it as a perk. Source: ESTV, salary certificate guidance 2026 (German).
  • Do you bill the electricity? Many companies charge employees a price per kWh through a badge system. If you resell electricity to third parties, the meter used for billing falls under the federal measuring instruments rules supervised by METAS.
  • Who pays for whose kWh? A separate meter or sub-meter for the charging circuit keeps the building's operating costs clean, which matters for a tenant company passing costs through its lease.

Data protection on site

A charging back-end records who charged, when and how much. In Switzerland, this is personal data under the revised Federal Act on Data Protection (nFADP / nDSG, in force since 1 September 2023). Three rules frame it:

  • the employer may only process employee data that relates to the job or is needed to perform the contract (Art. 328b of the Code of Obligations);
  • systems designed to monitor employees' behaviour are prohibited, and other control systems must be proportionate and announced in advance (Art. 26 of Ordinance 3 to the Employment Act, ArGV 3 / OLT 3);
  • if the back-end is hosted abroad, the transfer must meet the nFADP requirements.

In practice: keep charging logs for billing only, inform staff before the system goes live, and check where your provider stores the data.

What happens next: the timeline to watch

Date

Milestone

1 August 2026

City of Lucerne: C1 and C2 duties in force

12 October 2026

End of the federal consultation on the right to charge

2027 (expected)

Federal Council dispatch on the right to charge, then parliamentary debate

1 July 2027

Vaud: Article 42 of the new energy act on charging in force

2026 to 2030

Cantons transpose MuKEn 2025 into their law, at their own pace

2030

Schaffhausen: 2 % at level D in existing public car parks over 60 spaces

The dispatch date is our estimate: the Federal Council had not announced it at the time of this update. The SIA 2060 bulletin is also being revised, which may change the level definitions referred to by cantonal laws.

Checklist for each site

Before you sign a quote or a lease, answer these questions site by site:

  1. Which canton and municipality? Which energy law, building ordinance and municipal regulation apply?
  2. Is the project a new building, an extensive conversion or a main board replacement, which can trigger a duty?
  3. Which SIA 2060 level and which share of spaces are required, if any?
  4. Who owns the building: your company or a landlord (Art. 260a CO)?
  5. How much connection capacity is left, and is load management needed?
  6. Which vehicles really need to charge on site: pool cars, visitors, employees without home charging?
  7. How will employees' private cars be billed, and how is the data protected?

A site that answers "nothing required" to questions 2 and 3 can size its installation purely on real use.

Worked example: one group, three Swiss sites

An international group runs three Swiss sites in 2027:

  • New head office in Bern, 80 staff spaces: the building ordinance applies, so 16 spaces at level D and the rest at level A, shown in the energy proof with the building application.
  • Rented offices in Geneva, 30 spaces in an existing building: no quota for the company car park. Any charger needs the landlord's written consent, and the Geneva subsidies for pre-equipment target residential car parks, not offices.
  • Warehouse in the City of Lucerne, 40 company spaces, main board replaced: the replacement triggers the parking ordinance, so 8 spaces at level C2, with no charger required.

The same group therefore has three different answers: chargers in Bern, prepared cabling in Lucerne, and a negotiation in Geneva. A single group-wide car park standard either overshoots in Geneva or misses the Bern requirement.

Six common misconceptions

  • "EU rules apply in Switzerland too." False. The EU Energy Performance of Buildings Directive is not part of Swiss law. Cantonal and municipal law are what count.
  • "Every employer must offer charging points to staff." False. No provision obliges an employer to install chargers. For company cars, however, the 0.9 % private-use rule assumes the employer bears the energy cost, wherever the car charges.
  • "MuKEn 2025 already applies everywhere." False. It is a model, its e-mobility module is optional, and each canton decides whether and when to adopt it.
  • "The right to charge will force my commercial landlord to equip the car park." False, in the consultation draft. It covers residential buildings only.
  • "Level C1 means chargers." False. C1 and C2 are prepared cabling. Only level D means a working charger.
  • "Our existing car park is safe forever." Not necessarily. A main distribution board replacement in Lucerne, or an extensive conversion in Schaffhausen, is enough to trigger the rule.

Who does what in your company

Role

Responsibility

Facility or real estate manager

Cantonal and municipal rules per site, building permit, lease addendum with the landlord

Fleet manager

Real charging needs by vehicle profile, charge cards, home charging policy

HR and payroll

Tax treatment of free charging, salary certificate, reimbursement of home charging

Finance

Budget, depreciation of the installation, input VAT, recharging costs passed on to tenants or staff

IT and data protection

Charging back-end, data location, information of employees under the nFADP

The most expensive mistakes happen when the facility team sizes the car park alone, without the fleet data on where the cars actually sleep.

What it means for your fleet

The cantonal rules count spaces, not vehicles. MuKEn itself notes that most charging today takes place in buildings, at home and at work. For company cars parked overnight at the employee's home, home charging is the simplest and usually the cheapest option.

Worked example for a fleet based in the canton of Zurich:

  • mileage: 15,000 km per year per car;
  • consumption: 18 kWh/100 km, about 3,000 kWh at the meter including charging losses;
  • Zurich median 2026 (H4 profile, excl. VAT): 24.8 Rp./kWh;
  • home charging cost: about CHF 745.– per car per year.

Source: ElCom electricity prices by municipality. The real price depends on each employee's network operator and on high or low tariff periods.

To reimburse those kWh accurately, you do not need a connected wallbox at every employee's home. Voltaback reads charging data directly from the vehicle (more than 48 car brands connected) and applies the employee's real contract tariff. Voltaback relies on the home's MID-certified meter, not on a standalone cable meter. The measurement was audited by Bureau Veritas (1.22 % relative error), and the company never receives drivers' location data (nFADP / nDSG). Learn more about home charging reimbursement.

On site, size to real needs: first the cantonal and municipal minimum, then actual uses.

Vehicle profile

Where it charges

On-site need

Company car, driver with a parking space at home

At home, overnight

None, or occasional top-up

Company car, driver without a home charging option

At work and on the road

One point per few drivers, with load management

Pool car or service van returning to the site

In the company car park

One point per vehicle, or shared overnight

Visitors and employees' private cars

At work, occasionally

Small number of shared points, billed per kWh

Four in five Swiss EV drivers charge where they live, and only about 30 % occasionally charge at work. Source: TCS, 04.11.2025 (German). The installation recommendation simulator helps choose the right setup for each driver. If you are electrifying step by step, our article on fleet electrification sets out the method.

Frequently asked questions on EV charging obligations in Switzerland

Next steps

Start by checking your canton's and municipality's rules, site by site. Then size the rest to your fleet's real use, including home charging.

Managing a fleet in Switzerland? In 30 minutes we review the minimum for your sites and the real cost of your employees' home charging: talk to a Voltaback expert. For chargers on site, the charging station installation page explains how to obtain and compare installer quotes.